Scheduled Task doesn't run unless the EQ Scheduler Service is restarted
Article # 3015822 - Page views: 311
Problem Statement:
After upgrading from version 5.3 to 5.4 the Scheduled tasks are not running unless the EQ Scheduler Service was forced to restart. .
Cause:
This is a known issue in version 5.4 - Scheduler is not running all of the defined tasks and would only execute once the service had been restarted.
Resolution:
The issue can be resolved by applying Scheduler hotfix HF-237195-Scheduler (EQ54-HF-237195-Scheduler.msp) or higher.