How to force the Workqueue and the TakeNextActivity functionality to utilize the Job due date
Question / Problem:
I would like to force the Workqueue and the TakeNextActivity functionality to utilize the Job due date and not the activity due date. Since a job can have many activities, it does not make sense to have to update/modify these due dates multiple times when we could easily set it once on the job and have that be it..
Answer / Solution:
1. Job due dates ("Expected Duration") is shown below
2a. Activity due date ('Doc Review Due date) is shown below
2b. Activity due date (Validation Due Date) is shown below
.
You want (2a and 2b, doc review due date and validation activity due date) to only show/have Job due date (1).
If so; you can create a date variable and then open the Process extended properties and add the variables as shown below
All 3 due dates are the same. I added a date variable on each activity extended property.